Contractors in Michigan have a 90-day window from the last day of work to file a lien. If they miss this deadline, the lien is generally not valid. This rule applies to all contractors, including roofing companies. For specific advice, consult a local attorney.Full Conversation
I live in Michigan. A contractor is trying to put a lien on my house for payment but its past the 90 days
Hello ****. In Michigan:
*. Contractors have 90 days from the last day of work to file a lien.
*. If they miss this deadline, the lien is not valid.
Consider a legal consultation to ensure your rights are protected.
Can they file a lien after 90 days
In Michigan, contractors generally can't file a lien after 90 days from the last day of providing labor or materials. If they try to file a lien past this deadline, it's typically not valid. However, you should consult with a local attorney for specific advice.
Can a roofing company file a lien after 90 days
In Michigan, a roofing company, like any other contractor, generally has a *-day limit from the last day of work to file a lien. After this period, the lien may not be valid. It is recommended to seek advice from a local attorney for your specific situation.